Glossary · also called Mobilization advance, Mobilisation fund, Advance payment

Mobilisation Advance: Meaning and Recovery Example

Mobilisation advance: A mobilisation advance is an advance payment a client makes to a contractor at the start of a construction contract to help with site set-up, plant and initial material. It is usually a percentage of the contract value, often secured by a bank guarantee, and is recovered in instalments by deduction from later RA bills.

Definition

Starting a project costs money before any work can be billed: site offices, labour camps, plant, temporary works and the first materials. A mobilisation advance bridges that gap. It is not extra payment — it is the client’s money paid early, and it comes back to the client by deduction from the contractor’s bills.

The contract sets the terms: the percentage, whether interest is charged, the security required (commonly a bank guarantee), and when and how recovery happens. Some contracts also provide separate advances against plant or secured materials.

How it works

An example, with illustrative terms only: a ₹5 crore contract with a 10% mobilisation advance (₹50 lakh), recovered at 15% of the gross value of each RA bill until fully recovered.

Bill Gross value (₹) Recovery at 15% (₹) Balance outstanding (₹)
RA 1 60,00,000 9,00,000 41,00,000
RA 2 80,00,000 12,00,000 29,00,000
RA 3 1,00,00,000 15,00,000 14,00,000
RA 4 1,00,00,000 14,00,000 0

The recovery is one of several deductions on each bill, alongside retention money and, where applicable, liquidated damages.

Mobilisation advance vs secured advance

The two are often confused because both are recovered from RA bills.

Mobilisation advance Secured advance
Paid for Setting up the project: site, plant, first material Specific materials already brought to site but not yet used in the work
When At the start, before work is billed During the project, on a running bill
Security Usually a bank guarantee Usually the materials themselves, hypothecated to the client
Amount A percentage of contract value A percentage of the assessed value of those materials, set by the contract (for example, CPWD contracts allow up to 75%)
Recovery In instalments from later RA bills As the materials are used in the work, from the bills that measure that work

The exact terms always come from your contract.

Common mistakes

  • Treating the advance as income. It is a liability until recovered.
  • Losing track of the balance, so recovery continues after the advance is cleared or stops before it is.
  • Letting the bank guarantee lapse while a balance is still outstanding, or not reducing it as recovery progresses where the contract allows.
  • Ignoring the cash-flow dip. Recovery reduces net receipts in the middle of the project, when costs are often highest.
  • Spending the advance on another project. It was given to mobilise this one, and its recovery will come out of this project’s bills.

How GST applies to advances depends on whether they relate to supplies; check with your tax advisor.

In Zaptiz

Zaptiz Construction records the advance percentage at contract award, and its RA bills deduct advance recovery after retention, never more than the balance outstanding. The advance amount and recovery percentage can’t be entered in the app yet, so recovery shows ₹0 until they can. See RA billing software for the full billing flow.

All glossary terms

Construction ERP

Zaptiz Construction

For construction contractors — BOQ and tenders through project budgets, procurement, site progress, RA bills and payments.

Ready to modernise your business?

Whether you build electrical panels or deliver construction projects, Zaptiz brings your operations together on one platform.