How to prepare an RA bill: format, worked example and deductions
How to prepare a running account (RA) bill step by step: cumulative measurement, the standard format, retention, advance recovery, LD, TDS and GST on gross.
A running account (RA) bill is how most Indian construction contracts get paid: an interim bill for the work done so far, measured against the contract BOQ. This guide shows how to prepare one, what the format looks like, and how the deductions work, with a worked example. It is written for QS teams, project managers and accounts staff. If you are new to the term, start with what is an RA bill.
What you need before you start
- The contract BOQ, with item numbers, descriptions, units, quantities and rates. Every RA bill line comes from it.
- Measurements of work done to date, usually from the measurement book (MB) or joint measurement records signed on site.
- The previous bill as certified, not as claimed. Your “previous” figure is what the client allowed.
- The contract’s payment terms: retention percentage and any cap, advance recovery rate, LD clause, and the tax deductions that apply.
- Approved change orders for any extra or changed work. Without one, extra quantity has no contract rate.
Step 1: measure cumulatively, not monthly
Enter the total quantity executed to date for each BOQ item you are claiming, then subtract what was certified before. Measuring cumulatively means an error in one bill is corrected automatically in the next.
| Item | Unit | Rate (₹) | Qty to date | Prev. certified | This bill | Amount this bill (₹) |
|---|---|---|---|---|---|---|
| 2.1 PCC M15 | cum | 6,200 | 85 | 60 | 25 | 1,55,000 |
| 3.4 RCC M25 in columns | cum | 8,900 | 160 | 120 | 40 | 3,56,000 |
| 5.2 AAC block masonry | cum | 5,400 | 410 | 200 | 210 | 11,34,000 |
| Gross value of this bill | 16,45,000 |
Illustrative figures only.
Step 2: check against the contract quantity
Before you submit, compare every Qty to date with the BOQ quantity. If a line exceeds it, don’t bill the excess. Raise a change order and bill it once the client approves. Billing beyond the BOQ without approval is the quickest way to get a whole bill held back.
Step 3: the RA bill format
A typical RA bill has three parts:
- Abstract of measurement: the table above, item by item, with quantity to date, previous, this bill, rate and amount.
- Summary: gross value to date, gross value previously certified, and gross value of this bill.
- Deductions and net payable: everything the client holds back or recovers, and what is left to pay.
Number bills in sequence: RA 1, RA 2 and so on, with the last one marked final bill. Attach measurement sheets and the references to the MB pages.
Step 4: work out the deductions
Deductions come off the certified gross of the bill. A common order:
- Retention money: the contract percentage of the gross, often 5% to 10%, sometimes capped.
- Mobilisation advance recovery: the contract’s recovery rate, never more than the balance still outstanding.
- Material or secured advance recovery, where the contract has one.
- Liquidated damages, if delay is attributable to you.
- Income-tax TDS, deducted by the client under section 194C on contract payments, commonly 1% for an individual or HUF and 2% for others.
- GST TDS, for certain government clients, commonly 2% (1% CGST + 1% SGST, or 2% IGST) on contracts above the threshold.
Tax rates and thresholds change. Confirm them with your tax advisor for each contract.
Step 5: a worked example
Take the bill from Step 1, certified in full at ₹16,45,000, with 5% retention and 10% advance recovery:
| Amount (₹) | |
|---|---|
| Certified gross value | 16,45,000 |
| Less retention at 5% | 82,250 |
| Less mobilisation advance recovery at 10% | 1,64,500 |
| Net payable before tax deductions | 13,98,250 |
| GST at 18%, on the gross | 2,96,100 |
The important line is the last one: GST is charged on the gross value of work, not on the net. Retention and advance recovery are deductions from the payment, not reductions in the work you supplied. Charging GST on the net under-reports output tax, and it usually surfaces months later in GSTR reconciliation as amended returns and interest.
Income-tax TDS and any GST TDS then come off the payment the client actually makes, and you claim credit for them.
Step 6: submit, certify and invoice
- Submit the bill to the client’s engineer or consultant with the measurement records.
- The client certifies it, sometimes with reductions on individual lines. Record the certified figures, not your claim.
- Disallowed quantities aren’t lost: because you measure cumulatively, you claim them again in the next bill once the issue is settled.
- Raise the GST tax invoice for the certified amount.
- Record the payment against the invoice and reconcile any TDS.
Common mistakes
- Entering only this month’s quantity, so errors never get corrected.
- Using the previous claimed figure instead of the previous certified one.
- Billing extra work with no approved change order.
- Charging GST on the net instead of the gross.
- Losing track of retention across projects, so it is never claimed back after the defect liability period.
Doing it in Zaptiz Construction
Zaptiz Construction builds RA bills from the contract BOQ: you enter quantities to date and it works out this bill, refuses lines above the contract quantity until a change order is approved, keeps claimed and certified figures apart, holds retention in a register, and raises the GST invoice from the certified bill with GST on the gross. The RA Bill Drafting Assistant can propose the next bill’s quantities from executed and certified work for the QS to confirm.
For the step-by-step in the app, read Running RA bills in Zaptiz Construction, or see RA billing software for the overview. You can also open Zaptiz Construction and try it on a real bill.
Try it in Zaptiz
Construction ERP
Zaptiz ConstructionFor construction contractors — BOQ and tenders through project budgets, procurement, site progress, RA bills and payments.